A Comprehensive Guide On DNO Application

Do you have any questions regarding a DNO application? or what exactly a DNO is? You’re not alone who has wondered the same thing; many others have also done so. A distribution network operator is referred to as a DNO. They are businesses that manage electricity distribution, cables, and towers within their designated area. A G99 DNO application is required for any solar power system, including infrastructure for electric vehicle charging.

What is a DNO application?

A DNO application must be submitted to connect any solar power system to the appropriate distribution network operator. This process helps in estimating accurately how much electricity is required.

You need to fill out some forms before installing the solar generator, depending on its size. Typically, the rule is that you need more documentation for the more extensive system.

When installing a solar power system, the threshold typically falls over or under 16 amps per phase. The rated amp output of the inverter can be used as a guide. If you don’t know the amp rating, the electricians at the installation company can tell you.

AC output for small systems is less than 16 amps per phase. After registering, you can install these immediately by submitting a form to the DNO.

Systems with more than 16 amps per phase AC output are considered large. Before installing anything, you must fill out any necessary paperwork and contact your DNO for legal reasons. The DNO may take up to eight weeks to complete the procedure and review.

Results Of A DNO Application:

The DNO will make a connection offer after evaluating your DNO application. Typically, this includes the maximum connection specification and any additional fees. Your application evaluation can have three followings outcomes:

  • If your application has been accepted, and the DNO is satisfied with the requested system size. Then the installation can proceed without additional costs.

Note: The G99 relay mains protection ensures the safe operation of generators and the grid.

The size of the system has reached a certain kWp AC rating point, which indicates that there must be an export limitation. Make sure the limitation is followed.

Most of the time, the upgrade goes from single-phase to three-phase. You will be able to install and connect the system once the necessary work has been completed because the supply side needs to be upgraded. Then there will be an additional cost, which may be costly depending on the various sites.

Can The DNO Delay My Installation?

DNO Delays Due To Looped Supply:

A distribution network operator (DNO) is in charge of your home’s electrical supply, including the equipment in your meter box. Properties can sometimes be looped to neighbouring properties. Before an EV charger can be installed, the DNO will frequently insist on de-looping the properties in this situation.

DNO Delays Due To Fuse Upgrade:

A DNO estimates your property’s electrical demand and determines whether your main fuse can handle this demand. If not, it needs an upgrade that may take up to two months to complete.

DNO Delays Due To New Meter:

Your DNO may also want to install a new meter before installing an EV charger. 

DNO application is not a complex process when you have a better understanding of everything related to it, such as reverse power relay. It can provide protection against any unwanted damage to the turbine or motor upon a reverse power condition.